top of page

Create Your First Project

Start adding your projects to your portfolio. Click on "Manage Projects" to get started

Agile Transformation & Backlog Prioritization

Client

Established Technology Firm Undergoing Agile Transition

Industry:

Software as a Service (SaaS)

Tools & Platforms Used:

Jira, Confluence, Miro, Excel (initial backlog export), Agile frameworks (Scrum, Kanban)

Challenge:
The company was struggling with delayed releases, unclear priorities, and frequent misalignment between business stakeholders and the development team. Their backlog had grown cluttered with hundreds of items, with no clear structure or prioritization framework.

Objectives:

Transition the team from ad-hoc delivery to a structured Agile framework

Establish a clear backlog prioritization process

Improve collaboration between business stakeholders and development teams

Accelerate delivery of high-value features


Approach (Step-by-Step):

Discovery & Requirement Gathering: Conducted workshops with product managers, developers, and stakeholders to understand pain points in delivery and backlog management.

Agile Readiness Assessment: Assessed team maturity, existing processes, and tool usage. Identified gaps in sprint planning, backlog grooming, and communication.

Framework Design: Recommended a hybrid Agile approach (Scrum for feature development, Kanban for support tasks).

Backlog Audit & Prioritization:

Exported entire backlog from Jira.

Cleaned up duplicates, outdated, and irrelevant items.

Introduced MoSCoW and WSJF frameworks for prioritization.

Training & Workshops: Conducted hands-on sessions for product owners and stakeholders on backlog refinement, sprint planning, and user story writing.

Implementation:

Structured backlog with clear epics, user stories, and acceptance criteria.

Set up a cadence of backlog grooming and sprint planning sessions.

Introduced transparent prioritization dashboards in Jira.

Delivery & Change Management: Rolled out the Agile model gradually, with coaching support during first 3 sprints.

Results / Outcomes:

Backlog reduced by 45% (removal of redundant items).

Clear prioritization → top 20% of backlog items delivered within first 2 sprints.

Sprint velocity improved by 30% within 2 months.

Stakeholder satisfaction increased due to improved transparency and faster delivery.

Next Steps:
Suggested integrating AI-powered backlog refinement (using ChatGPT) to assist in user story drafting and acceptance criteria generation.

VizionIQ Global logo

Connect with me to explore how custom data strategies can elevate your business. Reach out via email or phone to initiate the journey towards optimized business performance.

Submit an Enquiry

Connect With Me:

  • LinkedIn
  • Facebook
  • Twitter

© 2025 VizionIQ.co.in.

All rights reserved.

bottom of page